Welding Cost Calculator
Estimate the filler metal, shielding gas, and labor cost of a weld from joint size, weld length, deposition rate, deposition efficiency, operating factor, and your own prices, using the standard weld-metal-weight costing method.
Results
Enter joint size, weld length, deposition rate, deposition efficiency, and operating factor to see the cost.
Usage examples
Quoting 20 m of 6 mm fillet weld
Enter carbon steel, a 6 mm leg, 20 m, 3 kg/h deposition rate, 95% efficiency, 30% operating factor, wire at 3.5/kg, labor at 45/h, and gas at 15 L/min and 8/m³. You need 2.83 kg of weld metal, 0.94 h of arc time, and 3.14 h of working time, for a total of 158.49 (7.92 per meter). Labor alone is 141.30 of that.
100 ft of 1/4" fillet in inch units
In imperial, enter a 1/4 in fillet, 10% reinforcement, 100 ft, 6 lb/h, 90% efficiency, 35% operating factor, wire at $2.80/lb, labor at $60/h, and gas at 35 CFH and $0.10/ft³. The job needs 11.70 lb of weld metal, 13.00 lb of wire, and 68.2 ft³ of gas, for a total of $377.46, or about $3.77 per foot.
Comparing two processes with different efficiency
Run 10 m of 8 mm fillet at the same 2 kg/h, 30% operating factor, filler at 4/kg, and labor at 40/h, changing only efficiency from 60% to 95%. Filler drops from 4.19 kg to 2.64 kg, but the total only moves from 184.21 to 178.04, showing that under these inputs deposition rate and operating factor drive the cost far more than efficiency.
Entering a V-groove butt weld by area
For 10 mm plate with a 60° included angle and a 2 mm root gap, the groove area is about 10² × tan 30° + 2 × 10 ≈ 77.7 mm². Choose 'Enter cross-section area', type 77.7, and use 5 m, 4 kg/h, 92% efficiency, and 40% operating factor: about 3.05 kg of weld metal and 1.91 h of working time.
Estimating time and consumables without prices
Leave the price fields blank and the costs show 0, but weld metal, filler needed, arc time, total working time, and gas volume are still calculated. That's handy for scheduling a job or deciding how much wire and gas to order.
Quick reference
Theoretical weld metal for equal-leg fillet welds (metric, no reinforcement)
| Leg size | Area (mm²) | Carbon steel (kg/m) | Stainless steel (kg/m) | Aluminum (kg/m) |
|---|---|---|---|---|
| 3 mm | 4.5 | 0.035 | 0.036 | 0.012 |
| 4 mm | 8 | 0.063 | 0.064 | 0.022 |
| 5 mm | 12.5 | 0.098 | 0.100 | 0.034 |
| 6 mm | 18 | 0.141 | 0.144 | 0.049 |
| 8 mm | 32 | 0.251 | 0.256 | 0.086 |
| 10 mm | 50 | 0.393 | 0.400 | 0.135 |
| 12 mm | 72 | 0.565 | 0.576 | 0.194 |
Theoretical weld metal for equal-leg fillet welds (inch, no reinforcement)
| Leg size | Area (in²) | Carbon steel (lb/ft) | Stainless steel (lb/ft) | Aluminum (lb/ft) |
|---|---|---|---|---|
| 1/8" | 0.0078 | 0.027 | 0.027 | 0.009 |
| 3/16" | 0.0176 | 0.060 | 0.061 | 0.021 |
| 1/4" | 0.0313 | 0.106 | 0.108 | 0.037 |
| 5/16" | 0.0488 | 0.166 | 0.169 | 0.057 |
| 3/8" | 0.0703 | 0.239 | 0.244 | 0.082 |
| 1/2" | 0.125 | 0.425 | 0.434 | 0.146 |
| 5/8" | 0.1953 | 0.665 | 0.677 | 0.229 |
Frequently asked questions
How does the calculator work out welding cost?
It uses the standard weld-metal-weight cost equations from Lincoln Electric's The Procedure Handbook of Arc Welding: filler cost = weld metal weight × filler price ÷ deposition efficiency; labor and overhead = weld metal weight × hourly rate ÷ (deposition rate × operating factor); gas cost = gas flow × arc time × gas price, where arc time = weld metal weight ÷ deposition rate.
What is deposition efficiency and where do I find it?
Deposition efficiency is the share of the filler metal you consume that actually ends up in the weld. Covered stick electrodes lose metal to stub ends, spatter, and slag, so they run lower than solid wire. The most reliable values come from the electrode or wire maker's data sheet, or from weighing filler before and after a test weld.
How do I choose the operating factor?
Operating factor is the percentage of total working time the arc is actually on. Fit-up, tacking, slag removal, repositioning, and changing wire or electrodes all lower it. It varies widely by process and shop, so the most accurate number comes from timing arc-on time over a few representative jobs in your own shop.
Why are there no default prices or efficiencies?
Filler and gas prices, labor rates, deposition rates, and efficiencies vary a lot by region, supplier, process, and welding parameters, so any single default would quietly produce wrong quotes. Every value is user-entered instead, and your inputs are saved in your browser so they are still there next time.
What does the fillet weld reference table assume?
It treats an equal-leg fillet as a flat-faced right isosceles triangle (area = leg² ÷ 2) multiplied by density. It does not include convexity, penetration, or oversize legs, so for real work add a reinforcement allowance (%) in the calculator.
How do I cost a groove (butt) weld?
Choose 'Enter cross-section area' and type in the groove area. For a single-V groove with no root face, plate thickness t, half the included angle θ, and root gap g, the area is roughly t² × tan θ + g × t. Add the weld cap with the reinforcement allowance (%).
Does it include electricity or equipment costs?
Electric power is not included because it needs separate voltage, current, and electricity-price inputs. Equipment depreciation, facility, and other overhead can be folded into the 'Labor + overhead rate' as an hourly figure, so they scale with working time.